When loads get too big for forklifts and too precise for rough handling, teams turn to overhead cranes. This field-tested breakdown follows the journey from bare runways to a commissioned crane ready for service. We’ll cover preparation and surveys—with the same checklists pro installers use.
What an Overhead/Bridge Crane Is
At heart, a bridge crane is a bridge beam that spans between two runway beams, carrying a trolley-mounted hoist for precise, vertical picks. The system delivers three axes of motion: cross-travel along the bridge.
You’ll find them in fabrication bays, steel plants, power stations, oil & gas shops, precast yards, and logistics hubs.
Why they matter:
Safe handling of very heavy, unwieldy loads.
Less manual handling, fewer delays.
Lower risk during rigging, lifting, and transport inside facilities.
Support for pipelines, structural steel, and big machinery installs.
What This Install Includes
Runways & rails: runway girders with crane rail and clips.
End trucks: motorized gearboxes for long-travel.
Bridge girder(s): cambered and pre-wired.
Trolley & hoist: cross-travel carriage with lifting unit.
Electrics & controls: VFDs, radio remote, pendant.
Stops, bumpers & safety: overload protection, e-stops.
Depending on capacity and span, you may be dealing with modest shop lifts or major industrial picks. The installation flow stays similar, with heavier rigs demanding extra controls and sign-offs.
Pre-Install Prep
A clean install is mostly planning. Key steps:
Drawings & submittals: Freeze the GA and verify reactions with the structural team.
Permits/JSAs: Permit-to-work, hot work, working at height, rigging plans.
Runway verification: Survey columns and runway beams for straightness, elevation, and span.
Power readiness: Lockout/tagout plan for energization.
Staging & laydown: Mark crane components with ID tags.
People & roles: Brief everyone on radio calls and stop-work authority.
Millimeters at the runway become centimeters at full span. Measure twice, lift once.
Rails & Runways
Runway alignment is the foundation. Targets and checks:
Straightness & elevation: Laser or total station to set rail height.
Gauge (span) & squareness: Check centerlines at intervals; confirm end squareness and expansion joints.
End stops & buffers: Verify clearances for bumpers at both ends.
Conductor system: Mount conductor bars or festoon track parallel to the rail.
Log final numbers on the ITP sheet. Misalignment shows up as crab angle and hot gearboxes—don’t accept it.
Lifting the Bridge
Rigging plan: Softeners protect painted flanges. Taglines for swing control.
Sequence:
Install end trucks at staging height to simplify bridge pick.
For double-girder cranes, lift both girders with a matched raise.
Use drift pins to align flange holes; torque to spec.
Measure diagonal distances to confirm squareness.
Prior to trolley install, bump-test long-travel motors with temporary power (under permit): ensure correct rotation and brake release. Re-apply LOTO once checks pass.
The Heart of the Lift
Trolley installation: Mount wheels, align wheel flanges, set side-clearances.
Hoist reeving: Check rope path, sheave guards, and equalizer sheaves.
Limits & load devices: Check overload/SLI and emergency stop.
Cross-travel adjustment: Align trolley rails on a double-girder.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
A smooth trolley with a quiet hoist is a sign of good alignment. Don’t mask issues with higher VFD ramps.
Electrics & Controls
Power supply: Conductor bars with collectors or a festoon system.
Drive setup: Enable S-curve profiles for precise positioning.
Interlocks & safety: E-stops, limit switches, anti-collision (if multiple cranes), horn, beacon.
Cable management: Secure junction boxes; label everything for maintenance.
Future you will too. Photos of terminations road grader help later troubleshooting.
QA/QC & Documentation
Inspection Test Plan (ITP): Hold/witness points for rail alignment, torque, electrical polarity, limit settings.
Torque logs: Record wrench serials and values.
Level & gauge reports: Note any corrective shims.
Motor rotation & phasing: Confirm brake lift timing.
Functional tests: Anti-collisions and zone interlocks.
A tidy databook speeds client acceptance.
Ready for Work
Static load test: Apply test weights at the hook (usually 100–125% of rated capacity per spec).
Dynamic load test: Travel long-run, cross-travel, and hoist at rated speed with test load.
Operational checks: Limit switches trigger reliably; overload trips; horn/beacon function.
Training & handover: Maintenance intervals for rope, brakes, and gearboxes.
When the logbook is clean, the crane is officially in service.
Everyday Heavy Lifting
Construction & steel erection: placing beams, trusses, and precast.
Oil & gas & power: moving heavy pumps, skids, and pipe spools.
Steel mills & foundries: hot metal handling (with the right duty class).
Warehousing & logistics: high throughput lanes.
Once teams learn the motions, cycle times drop and safety improves.
Do It Safe or Don’t Do It
Rigging discipline: rated slings & shackles, correct angles, spreader bars for load geometry.
Lockout/Tagout: test before touch every time.
Fall protection & edges: scissor lifts and manlifts inspected.
Runway integrity: no cracked welds, correct bolt grades, proper grout.
Duty class selection: match crane class to cycles and loads.
Safety isn’t a stage—it's the whole show.
Troubleshooting & Pro Tips
Crab angle/drift: verify end-truck wheel diameters and gearbox mounts.
Hot gearboxes: misalignment or over-tight brakes.
Rope drum spooling: check fleet angle and sheave alignment.
Pendant lag or dropout: antenna placement for radio; inspect festoon collectors.
Wheel wear & rail pitting: add rail sweeps and check clip torque.
Little noises are messages—listen early.
FAQ Snippets
Overhead vs. gantry? Bridge cranes ride fixed runways; gantries walk on the floor.
Single vs. double girder? Span and duty class usually decide.
How long does install take? Scope, bay readiness, and tonnage rule the schedule.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
What You’ll Take Away
Students and pros alike get a front-row seat to precision rigging, structural alignment, and commissioning. You’ll see how small alignment wins become big reliability wins.
Looking for a clean handover databook index you can reuse on every project?
Grab the installer pack so your next crane goes in cleaner, faster, and right the first time. Save it to your site tablet for quick reference.
...